Skip to main content

You designed the make ready, the attacher paid the estimate, the construction crew finished the route, and the new fiber is lit. On paper, the job is closed. Then someone pulls a fresh height photo on one of those poles and finds the new fiber sitting at 22'-4", higher than your make ready sheet called for, and the CATV line that was supposed to drop to 19'-6" still hanging at 20'-6", because that attacher never made its move.

That's the worked example in our own PCI training guide, and anyone who has spent time on make ready has seen some version of it on a real route. From the road, the pole looks finished. Nothing about it tells you that the clearance your engineer designed doesn't exist.

Most of the pole attachment process is built to get a job to construction: the application, the survey, the loading analysis, the estimate, the shot clock. Very little of it is built for the week after construction, when the only question left is whether the pole now matches the design. That's the question a post-construction inspection answers, and in a lot of joint use programs it still gets answered by a drive-by or not at all. We've done make ready engineering ourselves for a long time, and our view is simple: PCI is the cheapest place in the whole process to catch a mistake, and it's one of the steps programs skip most often.

This guide covers what PCI checks, when the FCC and pole owners require it, how an inspection runs from start to finish, where inspections usually go wrong, and how to do one without paying for a second full survey. If you'd rather see the workflow first, here's how Katapult Pro's engineering design tools carry the approved make ready design forward so every as-built photo gets checked against it.

What post-construction inspection means in pole attachments

A post-construction inspection (PCI) is a field check done after make ready and the new attachment are built. It compares the pole as it actually stands against the approved make ready design and the pole owner's construction standards. A good PCI produces two things: an as-built record of every attachment on the pole, and a list of anything that doesn't match, documented well enough to show who needs to fix it.

You'll hear it called by a few names depending on the agreement in front of you: as-built inspection, post-construction survey, post make ready inspection. Many pole attachment agreements define it in plain terms as the work of measuring or visually observing the licensee's attachments during or shortly after construction. The name matters less than the scope, and the scope is set by the work that was just done on that pole.

That scope is what separates PCI from the other field work on the same poles, which people on both sides of the pole tend to lump together:

Inspection

When it happens

What it answers

Pre-construction survey

Before make ready is designed

What's on the pole today, and what has to move to make room?

Post-construction inspection

After make ready and the new attachment are built

Does the pole match the approved design and the owner's standards?

Cyclical pole inspection

On the utility's routine inspection cycle

Is the pole itself still structurally sound?

Attachment audit

Periodically, across the whole system

Who is attached, and does the pole owner's record agree?


The pre-construction survey and the PCI are bookends, and when both are captured the same way, comparing them is quick. When they aren't, the inspection turns into a second survey.

Why post-construction inspections matter on a shared pole

A make ready design is a promise about clearances. It says the new fiber will sit at a certain height, the existing CATV will drop a foot, the telco cable will be bonded and lowered, and when all of that is done the pole will meet the NESC (or GO 95 in California) and the pole owner's construction standards. If construction doesn't match the design, the clearance the engineer calculated doesn't exist, and the next person to find that out may be a lineworker climbing the pole or a box truck passing under a midspan that sags lower than anyone planned.

PCI is also the moment the pole owner's record is cheapest to update. The design already says what should be on the pole, so the inspection only has to confirm it or record the difference. Skip it, and the record shows the proposed condition as if it were built, which is worse than an old record because nobody knows to question it. That record keeps paying off long after the attachment job closes; as-built documentation is what crews reach for when they're sorting out a pole strike, responding to a storm, or planning a new feeder.

Then there's the question of who pays. Under the FCC's pole attachment rules, a utility can't deny a new attacher access over a preexisting violation the new attacher didn't cause, and it can't charge the new attacher to bring a pole into compliance when someone else's earlier work put it out of compliance (47 CFR 1.1411). That puts real weight on the record of who built what, on which pole, and when. A PCI done at closeout draws the line between violations that came with the pole and violations that came with the last job, and it's a big part of what makes field data defensible when a reviewer or a cost dispute comes back to it months later.

Inspections also close a loop between engineering and construction. Engineers write make ready calls from experience and the pole owner's standards; construction crews see how those calls get built, pole after pole. When an inspection shows the same move built the same wrong way on twenty poles, look at the make ready note before you look at the crew, and fix it in the next design package.

As-built work also turns up things nobody expected to find. When TrueNet's fielding team rebuilt its as-built compliance process for federally funded broadband projects, the data showed terminals and drop heads on different poles than the design indicated. Their project manager put it plainly in our case study with TrueNet:

"The design says this is how it was built in the field. We get out there. That's not how it's built in the field."

Carl Gross, Project Manager, TrueNet Communications

Pole owners have noticed. National Grid, for example, notified third-party attachers in New York that every attachment application submitted after September 20, 2024 would be subject to a post-construction inspection billed to the applicant, with the stated goal of confirming compliance with the NESC and National Grid's own standards (National Grid notice). If you're an attacher or an engineering firm working in territories like that, PCI is now part of the job whether it was in your original estimate or not.

When the FCC and pole owners require PCI

The FCC's pole attachment rules write an inspection step into the two paths where the new attacher's own contractor performs make ready: one-touch make ready (OTMR) for simple make ready in the communications space, and self-help when the utility or existing attachers miss their make ready deadlines. In both cases, the pole owner and the existing attachers didn't do the work themselves, so the rules give them a defined window to check it. Both paths share the same timeline in 47 CFR 1.1411:

Step

Timeline

Who acts

Notice of completion

Within 15 days after make ready is finished on a particular pole

The new attacher notifies the utility and existing attachers

Inspection window

At least 90 days from receipt of that notice

The utility and existing attachers

Report of damage or code violations

Within 14 days after the inspection is complete, with adequate documentation

The utility or the existing attacher whose equipment was affected

Remedy

The notifying party fixes it and bills reasonable costs, or requires the new attacher to fix it at its own expense within 14 days

The notifying party chooses


The FCC's Fifth Report and Order reworked other timelines in the same section, including new tranches for mid-sized and large orders, and those amendments took effect May 7, 2026 (FCC public notice). The post-construction timeline in the table above is in the current rule text. Rules in this area keep moving, so check the current version of the section before you build a schedule around it.

Two caveats matter more than the table. The FCC rules apply where the FCC regulates pole attachments; states that have certified to regulate attachments themselves set their own procedures, and some are actively revising them. And outside OTMR and self-help, PCI is governed by the pole attachment agreement or tariff, which can look very different from the federal rule. One utility's published permit process, for example, requires the licensee's professional engineer or approved contractor to certify the post-construction inspection within 90 calendar days of installation, with the utility performing the inspection and charging for it if it waives the engineer requirement (permit process appendix). An older National Grid policy reserved the right to inspect within 30 days and allowed licensees, by mutual agreement, to perform the inspection themselves and avoid the fee.

So before the first post-construction photo gets taken, read the agreement for four things: who performs the inspection, how fast it has to happen, who pays for it, and what documentation the pole owner will accept.

What a post-construction inspection checks

The scope of a PCI comes from three places: the make ready design for the job, the pole owner's standards (the NESC or GO 95, plus the owner's own construction standards), and anything the attachment agreement adds. On most jobs, it comes down to the items below.

Attachment heights against the make ready design

Every attachment should sit where the design put it. The new attacher's cable should be at its proposed height, and every existing attacher called to move should have moved. The two misses we see described most often are the ones in the example at the top of this post: the new attachment placed a little higher or lower than proposed, and an existing attacher that hasn't made its move yet. The inspector's job is to record where each attachment actually is, not to assume the work was done because the job was marked complete.

Clearances to power and between communication attachments

Heights matter because of the clearances they produce: the separation between the top communication attachment and the lowest power facility on the pole, and the separation between communication attachments that the pole owner's standard requires. A move that's off by a few inches can break a clearance even when the heights look close, so the comparison works best when clearance rules are applied to measured heights rather than eyeballed.

Guying, anchors, and risers

A new attachment adds tension to the pole, and the make ready design usually accounts for it with new or modified guying. If the design called for a down guy and it isn't there, the loading analysis was run on a pole that doesn't exist. The inspection should capture reference photos of guys, anchors, risers, and any other make ready calls on the pole, and when the as-built differs from what was designed, the loading analysis should be rerun on the actual condition.

Midspan clearances

Clearance problems don't stay at the pole. Sag between poles determines clearance over roads, driveways, and other wires, and a new attachment placed higher or lower than designed changes what happens in the span. Midspan photos need their own height reference, because there's no pole in the frame to measure against; in our workflow that means a height stick in every midspan PCI photo.

Pole replacements and transfers

When make ready includes a pole replacement, the old pole stays up until every attacher transfers to the new one, and that's how double wood happens. A PCI on a replaced pole is a natural point to record which attachers have transferred and which haven't, which gives the pole owner something concrete to act on instead of a vague backlog. It's also a different inspection technically: every height reference from the original photo is gone with the old pole, so the new pole needs a full height photo with a measuring stick.

Damage to existing facilities

The FCC rule covers damage as well as code violations, and so do most agreements. Damaged cable, crushed or misplaced hardware, and equipment knocked out of position during make ready all belong in the inspection record, with photos.

How a post-construction inspection works, step by step

We run PCI in Katapult Pro, and the tool names below come from our Katapult Pro PCI guide. The order holds whatever tools you use.

1. Freeze the approved design before construction starts

The inspection has to compare the as-built pole against the design that was approved, not a version that's been edited since. In Katapult Pro, the Prep for Post Construction tool saves a snapshot of the job in its pre-construction state, adds the PCI attributes to the job, and resets the completion flags so the poles can be collected again. The original photos get a "Pre-Construction" watermark so nobody confuses them with the new ones.

2. Collect post-construction photos once the completion notice arrives

Schedule fieldwork as soon as construction is reported complete. Under the FCC timeline, the clock starts when the notice is received, and you'll want room left over for the 14-day reporting window. For a pole that wasn't replaced, the field crew needs a height photo (no measuring stick required) plus reference photos that show guying, risers, and any other make ready calls. For a replaced pole, the crew takes a full height photo with the stick against the new pole. Midspan photos need the stick in the span.

3. Upload the photos and associate them with poles

Photos go through the same upload, classification, and association steps as the original survey. Katapult Pro associates photos to pole locations by timestamp when they're uploaded, so the camera's clock has to be set correctly before the crew leaves the yard. A clock set to the wrong time zone puts photos on the wrong poles.

4. Calibrate the new photo from heights that didn't change

Because the original height photo was calibrated, the new photo can borrow its measurements. The PCI routine in Katapult Pro walks through the markers on the pre-construction photo, and you click the matching heights on the new photo to place four calibration points. Pick points that couldn't have moved: the top of the pole if it wasn't replaced, attachments and equipment that weren't called to move, the bottom of the pole tag. Never use a proposed cable height or anything the make ready called to move. Spread the four points out across the pole, and when the calibration is good, the calibration line turns green.

5. Transfer the design onto the as-built photo

With Apply Make Ready Moves checked, Transfer Heights places every attachment marker on the new photo at its proposed position. The photo now shows where everything should be. Wherever a wire in the photo doesn't line up with its marker, the gap between design and construction is visible immediately. If you can already see that an attacher hasn't moved, you can select that wire and transfer it at its original height instead, which saves time on the corrective make ready.

6. Mark what's actually there and call corrective make ready

Move each marker to where its attachment actually sits. Clearance violations recalculate from the real heights, and the engineer calls new make ready to fix anything that's out of compliance, with notes for each move. Where a violation existed before the job started, filtering the pole by attachment owner (the same approach we use for forensic make ready) shows who it belongs to, which matters for the cost question above.

7. Send documented findings and close out the pole

Download the make ready notification for the PCI so it includes every new move and note, and send it to the parties responsible. Under the FCC rule, findings go out within 14 days of the inspection with adequate documentation, and a calibrated photo with measured heights marked on it is about as clear as documentation gets. Once you exit the PCI view, the post-construction photo becomes the main photo for the pole, so the job record now reflects what was built rather than what was proposed.

Post-construction inspection shouldn't cost as much as the survey that came before it. In Katapult Pro, the calibrated photos and make ready design from the original job carry straight into the inspection, so a pole that wasn't replaced needs a new height photo and a few reference shots instead of a full remeasure. Book a call with our team to walk through a PCI on one of your own routes, or read the step-by-step PCI guide first.

Why PCI gets skipped, and how to make it affordable

The honest reason PCI gets skipped is cost. Done the traditional way, a post-construction inspection means another rideout and a new set of measurements on every pole, which makes it only marginally cheaper than the original engineering survey. It usually lands after the attacher's budget has been spent and the network is already in service, and the contract often doesn't say clearly who's paying for it. On a deployment racing a funding deadline, closeout is the first thing to slide.

The way around that is to stop treating the inspection as a new survey. The original job already holds a calibrated photo of every pole, so the post-construction photo can be calibrated from heights that are already known. When we first tested this in 2019, we calibrated a photo snapped on an uncalibrated tablet using heights measured in the first photo, and the method has been part of Katapult Pro's PCI workflow ever since. It has real limits: it doesn't work on a replaced pole, and midspans still need a stick in the shot. But for the majority of poles on a typical route, which weren't replaced, it takes most of the measuring out of the inspection.

It also changes who can capture the as-built photo. Without the stick, a construction crew could take it before leaving the pole, which saves a trip if the pole owner's agreement lets the attacher's side submit inspection photos. Have that conversation with the pole owner before the job starts.

The other half of making PCI affordable is pricing it in from the beginning. If the inspection is part of the make ready engineering scope on day one, with the pre-construction snapshot captured before the first crew rolls, it stops being the line item that gets cut at the end of the job.

Software and tools for post-construction inspection

A post-construction inspection touches four kinds of tools, and it goes faster when they share one record of the pole instead of passing spreadsheets between them.

Field collection. Photo-based measurement, where a calibrated height photo produces attachment heights in the office, leaves reviewable evidence of what was on the pole the day it was captured. Manual measurements can be accurate, but they leave nothing to look back at when a finding gets disputed. We've written more about why field data collection still starts at the pole.

Engineering design and comparison. The approved design has to be in a form you can compare against, with the pole owner's clearance rules applied, so violations get flagged and corrective make ready gets written in one place.

Pole loading analysis. When the as-built differs from the design (an attachment higher than proposed, a missing down guy), loading should be checked on the actual condition. SPIDAcalc, O-Calc Pro, and PoleForeman are the tools most pole owners specify for that analysis.

Joint use and notification systems. Findings have to reach the right attacher, and transfers on replaced poles have to get tracked. That usually means the pole owner's application portal, NJUNS for transfer notifications, and eventually the utility's GIS, which stays the system of record.

Katapult Pro sits in the middle of that as the work-in-progress layer. It holds the pre-construction snapshot, the as-built photos, the height comparison, and the corrective make ready, then hands the results to the tools downstream. It doesn't replace the utility's GIS or the loading tool the pole owner mandates; Katapult Pro runs loading as you design and exports to SPIDAcalc and O-Calc Pro when the pole owner wants the analysis in their format. For pole owners, the same data feeds a joint use program that tracks each application against the FCC shot clock.

See how a job moves from field data collection through design and into the inspection, then book a call with our team to walk through how your pole owner wants PCI findings documented.

Frequently asked questions about post-construction inspection

What does PCI stand for in pole attachments?

PCI stands for post-construction inspection. It's the field check, done after make ready and a new attachment are built, that confirms the pole matches the approved make ready design and the pole owner's standards, and documents anything that doesn't.

Is post-construction inspection required by the FCC?

The FCC's pole attachment rules build an inspection window into one-touch make ready and self-help make ready, where the new attacher's contractor does the work. The new attacher must give notice within 15 days of finishing make ready on a pole, and the utility and existing attachers get at least 90 days to inspect. Outside those paths, PCI requirements come from the pole attachment agreement or, in states that regulate attachments themselves, from state rules.

How long does a pole owner have to inspect make ready work?

Under the FCC rules for one-touch and self-help make ready, the utility and existing attachers have at least 90 days from receiving the completion notice. They then have 14 days after finishing the inspection to report damage or code violations, with documentation. Agreements outside the FCC framework set their own windows, which can be much shorter.

Who pays for a post-construction inspection?

It depends on the agreement. Many pole owners bill the attacher for the inspection itself, and some allow the attacher's engineer or approved contractor to perform it instead. For fixing what the inspection finds, the FCC rules for one-touch and self-help make ready put the cost of damage or code violations caused by the new attacher's work on the new attacher.

What's the difference between a post-construction inspection and a pole audit?

A post-construction inspection is scoped to one job: it checks the poles where make ready was just performed against that job's design. A pole audit, or attachment audit, covers the whole system periodically to find out who is attached and whether the pole owner's records agree, including attachments that never went through an application.

Do you need a full resurvey to do a post-construction inspection?

Not for most poles. If the original survey produced calibrated height photos, a new photo of an unreplaced pole can be calibrated from heights that didn't change, and the make ready design can be transferred onto it for comparison. Replaced poles and midspans still need a height reference in the photo.

Making PCI part of how make ready closes

Post-construction inspection is easy to skip because nothing breaks the day you skip it. The violation sits on the pole until a storm, a pole strike, or the next attacher's survey finds it, and by then nobody remembers which job put it there. Most of the fix is scheduling and scope: capture the snapshot before construction, agree with the pole owner on the documentation they'll accept, and put the inspection in the make ready estimate.

None of this makes joint use simple. Agreements vary by pole owner, state rules keep changing, and transfers on replaced poles will drag no matter how good the inspection is. But a pole that's been inspected and recorded after construction is a pole the next engineer, the next attacher, and the next lineworker can trust.

Book a workflow review with our team and bring a recent job; we'll walk through what a PCI on it looks like in Katapult Pro. If you run the pole owner side of a joint use program, start with how Joint Use Management tracks every application against the FCC shot clock.

 
 
 

© 2026 Katapult Pro. All rights reserved.

  • LinkedIn
  • Youtube
  • Instagram